05 March 2015

Fuselage: Forward mid fuselage lower structure. Completed.

The firewall has been sealed on to the lower fuse skins and muffler shrouds.



After I sealed everything together, I realized I neglected to rivet the F-01435-L/R cover bases to the F-01451-L/R tunnel sides.  There are 2 rivets on each side that need to be set before attaching everything to the F-01483-L/R forward bottom skins.  If they aren't done prior to that point, then there won't be access to the inboard side of the tunnel sides since the F-01453-L/R muffler shroud sides would be in the way.  See red areas below from page 28-05.


Figuring I'd have to use a pull rivet of some kind, I researched my options.  I found that there are no strong 3/32" pull rivets available.  The best I found was the CCC-32, which has relatively poor strength.  So, I thought I might be able to uncleco the tunnel sides to access the rivets.  Sure enough, it was possible.  With some wood blocks to push the sides away from the muffler shroud, I could easily negotiate a squeezer in there.  Crisis averted.


04 March 2015

Fuselage: Forward mid fuselage lower structure. Muffler shrouds on.

For the side shrouds, I did two things contrary to plans:
  1. I did not rivet the F-01453-L/R muffler shroud doublers and F-01465 muffler hanger angles to the shroud sides until after the shroud sides were themselves riveted to the bottom skins.  I saw that the muffler doublers and angles would impede rivet access on the flanges of the shroud sides.  I tested to ensure I could access the doubler and hanger rivets with my squeezer once the sides were riveted down.
  2. I decided to seal and rivet the F-01454 muffler shroud ramp following riveting of the shroud sides because I thought it would be easier to manage riveting the shroud sides without the ramp in the way and wobbling around a lot.
So....after I sealed the F-01453-L/R muffler shroud sides to the F-01483-L/R forward bottom skins, I set the assemblies aside for a few days to let the sealant cure a bit to reduce mess, as shown in the left image.  The right image shows the riveted assemblies. 

\

I back riveted all of the rivets save the aft 5 rivets on each side.  For those boys, I had to get creative, as I work mostly alone.  A combination of holding the skin with my legs and trapping the assembly between my EAA Chapter 1000 workbenches, let me finish off those aft rivets.



Here is the inboard side of the muffler doubler (left) and muffler hanger (right) for the left assembly.  The excess sealant at bottom of the image is easily cut away later.


Next, the muffler shroud ramp needs to be sealed in.  First, I decided to wipe a thin layer of sealant on the flanges of the shroud sides and ramp to make sure I wasn't completely reliant on an exterior, exposed fillet of sealant as suggest in the plans.

Then I cleco'd the ramp to the right shroud side first.


Then using the space between my EAA Chapter 1000 workbenches, I inverted the forward bottom skins so the shroud could fit between them and cleco'd in the left side shroud.  Access isn't as easy, but my back is good for it.


Next a sealant fillet is applied and smoothed with a Popsicle stick.  Close up of the fillet (left) and looking down (well, up really) the ramp (right).


And here the assembly sat for a few days to let the sealant cure a bit before final riveting.  Thankfully, the riveting of the ramp to the shroud sides can be done with a squeezer.  The boards were to keep the skins straight and weighted down so the latter could keep their shape during sealant curing.


For the aft-most 2 rivets that fasten the shroud sides to the ramp, I could not get a squeezer yoke to fit in there nor could I get a bucking bar in there.  However, I had a long, thin steel bar I obtained for one of the harder-to-reach rivets on the rudder (it didn't work very well for that purpose).  I used that rod with another bucking bar as a fulcrum to help keep pressure against the shop head.  A couple of Popsicle sticks on one side of the bar helped angle the bar to match that of the rivet to prevent the latter from clenching over.  Worked great.


Completed assembly awaiting mating to the firewall.


03 March 2015

Fuselage: Upper forward fuselage. Upper forward fuselage assembly completed.

This is a fairly straight forward part. As I typically work solo, I have to support my work so I have something to work against when applying forces to rivet.


I would suggest riveting the F-01477-L/R connector brackets to the F-01494-L/R instrument panel standoffs before riveting the standoffs to the upper forward fuse assembly.  Putting the brackets on earlier does not impede access to the rivets attaching the standoffs to the assembly.


I was able to squeeze the aft-most rivets.  But it's extremely difficult to access the forward-most AN426AD3-3.5 rivet on each bracket.  I had to come up with a creative way to do it.  Below you can see how I situated a back rivet plate in just the right location.  With my 12" extended back rivet set, I was able to hit it. 


The upper forward fuselage assembly awaits its turn to be fastened to the upper forward fuselage.



25 February 2015

Fuselage: Forward mid fuselage side structure. Longerons continued.

Following the original preperation of the F-01418A-L/R upper longerons, it was time to continue their plight.

On first look, the F-01488-L/R upper engine mounts seem identical.  However if you inspect them carefully, you'll notice the forward face has a very slight angle to the vertical.  Stare at it long enough and you'll see it.  So, it's easy to interchange these parts even after match drilling.  I happened to lose track of -L/R during priming.  Below is a disambiguation image provided to me by Van's.  Note:  In the image, the part is oriented upside down relative to installation.


Below shows the right side mount upside down (bottom side facing upwards) with its forward face against a 90 degree edge.  You can see the 90.6° angle subtly subtended by the two edges via noting the progressively larger gap going upwards.


Left F-01418A-L upper longeron and engine mount installed, top (left) and bottom (right).
 

Right F-01418A-R upper longeron and engine mount installed, top (left) and bottom (right).  The forward-most CherryMax on the top (left) isn't ideal however it does meet the spec (page 14 of the CherryMax Process Manual).


Now for the F-01444-L/R lower longerons, it's easy to lose track of which side is left and which is right when dealing with the longer doublers F-01444A-L/R, especially once you separate them from themselves.


I had fastidiously labeled each side, but following the priming process, like with the upper engine mounts, I lost track.  Luckily, I had some pictures of a fuselage in progress at Van's which made it clear to me how to orient the parts (further confirmed on VAF).  Below shows the proper way.


When I went to put in the CR3213-4-5 CherryMAX rivets, having little experience with them and being calibrated to standard AN426/470AD4s, I thought the Cherrys(ies?) looked too short for the material thickness. 


After learning about CherryMAX rivets from this Cherry Aerospace pdf, I found that the "-5" indicated a maximum grip length of 5/16".  Measuring the thickness of the parts found 0.285" which is 4.56/16".  Thus a -5 is the appropriate length given that the next smaller size is -4, making it too short.

Completed lower longeron assemblies showing the F-01489-L/R lower engine mount brackets.  Interesting CherryMAX shop heads.  They appear to be acceptable (page 14 of the CherryMax Process Manual).


22 February 2015

Fuselage: Forward mid fuse bulkheads. Forward center completed.

Remarkably, I finally completed the forward center bulkhead.  What was holding me up was my third and finally successful attempt at the right bearing bracket assembly.  See here for details on try #1 and here for try #2.

It is my suggestion to rivet the F-01441-L/R bearing bracket braces to their respective inboard F-01438-L/R cover ribs prior to riveting those ribs to the F-01403 forward center section bulkhead.  The plans have you rivet the braces after the cover ribs get riveted to the bulkhead.  That makes accessing the rivets holding the braces to the ribs difficult (see below).  I see no impediment to accessing the rivets holding the cover ribs to the bulkhead with the brace riveted on beforehand.


I have no isolated picture of the completed bulkhead, as I attached it to the lower forward fuselage prior to thinking of capturing an image.